Statut : Annulé / suppriméDate de publication : 09/09/2024 17:21:37Date de début : 21/12/2023 15:51:12Société : EDF
Taking into account key learnings from controls and repairs undertaken in 2023 on reactors linked to stress corrosion cracking, EDF considers that, in 2023, one planned outage out of three for the following reactors may be extended by an average of 30 days.
The reactor(s) concerned : -
-
-
Version antérieure du message - v5
-
Statut : InactifDate de publication : 11/04/2024 12:13:26Date de début : 21/12/2023 15:51:12Société : EDF
Taking into account key learnings from controls and repairs undertaken in 2023 on reactors linked to stress corrosion cracking, EDF considers that, in 2023, one planned outage out of three for the following reactors may be extended by an average of 30 days.
The reactor(s) concerned : BUG3.
-
-
Version antérieure du message - v4
-
Statut : InactifDate de publication : 28/03/2024 13:09:20Date de début : 21/12/2023 15:51:12Société : EDF
Taking into account key learnings from controls and repairs undertaken in 2023 on reactors linked to stress corrosion cracking, EDF considers that, in 2023, one planned outage out of three for the following reactors may be extended by an average of 30 days.
The reactors concerned are: CHB1, BUG3.
-
-
Version antérieure du message - v3
-
Statut : InactifDate de publication : 29/02/2024 10:30:05Date de début : 21/12/2023 15:51:12Société : EDF
Taking into account key learnings from controls and repairs undertaken in 2023 on reactors linked to stress corrosion cracking, EDF considers that, in 2023, one planned outage out of three for the following reactors may be extended by an average of 30 days.
The reactors concerned are: BLA2, CHB1, BUG3.
-
-
Version antérieure du message - v2
-
Statut : InactifDate de publication : 27/02/2024 10:42:29Date de début : 21/12/2023 15:51:12Société : EDF
Taking into account key learnings from controls and repairs undertaken in 2023 on reactors linked to stress corrosion cracking, EDF considers that, in 2023, one planned outage out of three for the following reactors may be extended by an average of 30 days.
The reactors concerned are: BLA2, CHB1, BUG3, DAM3 .
-
-
Version antérieure du message - v1
-
Statut : InactifDate de publication : 21/12/2023 15:51:56Date de début : 21/12/2023 15:51:12Société : EDF
Taking into account key learnings from controls and repairs undertaken in 2023 on reactors linked to stress corrosion cracking, EDF considers that, in 2023, one planned outage out of three for the following reactors may be extended by an average of 30 days.
The reactors concerned are: BLA2, GRA2, CHB1, BUG3, DAM3 .
-