EDF-2023-00222
-
Version actuelle du message - v5
-
Statut : Annulé / suppriméDate de publication : 04/12/2024 02:53:28Date de début : 11/12/2023 19:28:46Société : EDF
End of message
-
-
Version antérieure du message - v4
-
Statut : InactifDate de publication : 06/06/2024 19:22:40Date de début : 11/12/2023 19:28:46Société : EDF
Publication on behalf of EDF-Renewables
On June 6th 2024, 97 MW additional capacity of Parc Eolien Offshore des Hautes Falaises (Fécamp) has been commissioned.
The dates for the main commissioning phases of the offshore wind farm are as follows
100 MW: September 1st, 2023 (confirmed)
200 MW: December 11th 2023 (confirmed)
300 MW: March 15th2024 (confirmed)
400 MW: May 10th 2024 (confirmed)
497 MW: June 6th 2024 (confirmed)
-
-
Version antérieure du message - v3
-
Statut : InactifDate de publication : 29/04/2024 20:09:00Date de début : 11/12/2023 19:28:46Société : EDF
Publication on behalf of EDF-Renewables
Offshore Windfarm under construction
On March 15th 2024, 100 MW additional capacity of Parc Eolien Offshore des Hautes Falaises (Fécamp) has been commissioned.
100 MW: September 1st, 2023 (confirmed)
200 MW: December 11th 2023 (confirmed)
300 MW: March 15th 2024 (confirmed)
400 MW: April 29th 2024
Estimated dates for next commissioning phases of the wind farm:
497 MW: May 2024
These dates will be updated on a regular basis during the commissioning process.
-
-
Version antérieure du message - v2
-
Statut : InactifDate de publication : 15/03/2024 13:02:54Date de début : 11/12/2023 19:28:46Société : EDF
Publication on behalf of EDF-Renewables
Offshore Windfarm under construction
On March 15th 2024, 100 MW additional capacity of Parc Eolien Offshore des Hautes Falaises (Fécamp) has been commissioned.
100 MW: September 1st, 2023 (confirmed)
200 MW: December 11th 2023 (confirmed)
300 MW: March 15th 2024 (confirmed)
Estimated dates for next commissioning phases of the wind farm:
400 MW: April 2024
497 MW: May 2024
These dates will be updated on a regular basis during the commissioning process.
-
-
Version antérieure du message - v1
-
Statut : InactifDate de publication : 11/12/2023 19:29:05Date de début : 11/12/2023 19:28:46Société : EDF
Offshore Windfarm under construction
On December 11th 2023, 100 MW additional capacity of Parc Eolien Offshore des Hautes Falaises (Fécamp) has been commissioned.
100 MW: September 1st, 2023 (confirmed)
200 MW: December 11th 2023 (confirmed)
Estimated dates for next commissioning phases of the wind farm:
300 MW: January 2024
400 MW: March 2024
497 MW: April 2024
These dates will be updated on a regular basis during the commissioning process.
-