EDF-2021-00035

  • Version actuelle du message - v10
    • Statut : Annulé / supprimé
      Date de publication : 15/01/2024 17:34:59
      Date de début : 29/01/2021 13:16:22
      Société : EDF

      End of the specific management of modulation of Paluel 2 power unit. The plant will not restart before the end of the next maintenance, starting on 04/06/2022.

  • Version antérieure du message - v9
    • Statut : Inactif
      Date de publication : 20/05/2022 16:45:55
      Date de début : 29/01/2021 13:16:22
      Société : EDF

      End of the specific management of modulation of Paluel 2 power unit. The plant will not restart before the end of the next maintenance, starting on 04/06/2022.

  • Version antérieure du message - v8
    • Statut : Inactif
      Date de publication : 15/02/2022 11:29:30
      Date de début : 29/01/2021 13:16:22
      Société : EDF

      Paluel 2 power unit will have to be stopped for 6 weeks for modulation by its next maintenance planned in week 23 in year 2022. The positioning of these modulation weeks is provisional.

  • Version antérieure du message - v7
    • Statut : Inactif
      Date de publication : 15/02/2022 11:05:38
      Date de début : 29/01/2021 13:16:22
      Société : EDF

      Paluel 2 power unit will have to be stopped at least for 7 weeks for modulation by its next maintenance planned in week 23 in year 2022. The positioning of these modulation weeks is provisional.

  • Version antérieure du message - v6
    • Statut : Inactif
      Date de publication : 23/08/2021 12:31:27
      Date de début : 29/01/2021 13:16:22
      Société : EDF

      The Paluel 2 power unit will have to be stopped at least for 7 weeks for modulation by its next maintenance planned in week 23 in year 2022. The positioning of this modulation weeks is provisional: it will be reassessed and the plant will be restarted if economically justified.

  • Version antérieure du message - v5
    • Statut : Inactif
      Date de publication : 19/08/2021 09:46:38
      Date de début : 29/01/2021 13:16:22
      Société : EDF

      The Paluel 2 power unit will have to be stopped at least for 8 weeks for modulation by its next maintenance planned in week 23 in year 2022. The positioning of this modulation weeks is provisional: it will be reassessed and the plant will be restarted if economically justified.

  • Version antérieure du message - v4
    • Statut : Inactif
      Date de publication : 04/08/2021 17:16:52
      Date de début : 29/01/2021 13:16:22
      Société : EDF

      The Paluel 2 power unit will have to be stopped at least for 10 weeks for modulation by its next maintenance planned in week 23 in year 2022. The positioning of this modulation weeks is provisional: it will be reassessed and the plant will be restarted if economically justified.

  • Version antérieure du message - v3
    • Statut : Inactif
      Date de publication : 28/07/2021 16:35:24
      Date de début : 29/01/2021 13:16:22
      Société : EDF

      The Paluel 2 power unit will have to be stopped at least for 11 weeks for modulation by its next maintenance planned in week 23 in year 2022. The positioning of this modulation weeks is provisional: it will be reassessed and the plant will be restarted if economically justified.

  • Version antérieure du message - v2
    • Statut : Inactif
      Date de publication : 22/02/2021 15:33:27
      Date de début : 29/01/2021 13:16:22
      Société : EDF

      The Paluel 2 power unit will have to be stopped at least for 13 weeks for modulation by its next maintenance planned in week 23 in year 2022. The positioning of this modulation weeks is provisional: it will be reassessed and the plant will be restarted if economically justified.

  • Version antérieure du message - v1
    • Statut : Inactif
      Date de publication : 29/01/2021 13:16:59
      Date de début : 29/01/2021 13:16:22
      Société : EDF

      The Paluel 2 power unit will have to be stopped at least for 12 weeks for modulation by its next maintenance planned in week 23 in year 2022. The positioning of this modulation weeks is provisional: it will be reassessed and the plant will be restarted if economically justified.