EDF EDF-2024-00319 20/12/2024 02:49:31 Active

Due to an IT problem, EDF cannot publish unavailabilities to the "Unavailability of generation resources" RTE webpage.
Until resolution, any significant change in EDF generation units availabilities are still published on the following webpage :
https://www.edf.fr/groupe-edf/ambition-neutralite-co2-pour-edf-a-l-horizon-2050/optimisation-et-trading/listes-des-indisponibilites-et-des-messages/liste-des-indisponibilites

EDF EDF-2024-00318 20/12/2024 02:49:16 Active

Un dysfonctionnement informatique affecte les publications concernant le parc de production d'EDF vers la partie "indisponibilités des groupes de production" du site RTE. En attendant la reprise normale du service, vous pouvez continuer de suivre toute évolution significative de la disponibilité du parc EDF à l'adresse : https://www.edf.fr/groupe-edf/ambition-neutralite-co2-pour-edf-a-l-horizon-2050/optimisation-et-trading/listes-des-indisponibilites-et-des-messages/liste-des-indisponibilites

EDF EDF-2024-00317 19/12/2024 18:34:32 Active

A la suite d'une contractualisation avec RTE, la puissance disponible cumulée des tranches Dampierre 1, 2, 3 et 4 sera limitée à 2700 MW pour des contraintes réseau du 14/01/2025 00h au 15/01/2025 00h.

---

Due to an agreement following a request from RTE, the cumulative production of Dampierre 1, 2, 3 and 4 will be limited to 2,700 MW for grid constraints from 14/01/2025 00:00 to 15/01/2025  00:00.

 

EDF EDF-2024-00316 19/12/2024 18:32:27 Active

A la suite d'une contractualisation avec RTE, la puissance disponible cumulée des tranches Dampierre 1, 2, 3 et 4 sera limitée à 2700 MW pour des contraintes réseau du 23/12/2024 07h30 au 24/12/2024 17h.

---

Due to an agreement following a request from RTE, the cumulative production of Dampierre 1, 2, 3 and 4 will be limited to 2,700 MW for grid constraints from 23/12/2024 07:30 to 24/12/2024 17:00.

 

EDF EDF-2024-00315 18/12/2024 14:44:03 Active

Passage en DMO 13h pour le CCG de Martigues 5 jusqu'à nouvel avis (6h30 pour le couplage et 6h30 pour atteindre la PMD)
-----------------------------
Until further notice increased time of 13 hours for coupling and ramp-up to full load for the CCG unit of Martigues 5 (6.5 hours for coupling and 6.5 hours for reaching full load).

EDF EDF-2024-00125 18/12/2024 11:22:07 Active

Flamanville 3 EPR (Message 2/2)
The volume of electricity produced from the first grid connection until the first planned outage called "VC1" will be around 14 TWh. 

This first planned outage should mainly take place in 2026. Its organization, content and subsequent duration are under construction.

EDF EDF-2024-00124 18/12/2024 11:20:25 Active

Flamanville 3 EPR (Message 1/2)
The first connection to the grid of Flamanville 3 is scheduled for December 20, 2024. After its connection, the reactor will be operated at different capacity levels until summer 2025, which will conclude the testing phase. 

At the end of this testing period, the unit is expected to be operated at 100% capacity until the first planned outage for maintenance and refueling, called Visite Complète 1 (VC1).

EDF EDF-2024-00123 18/12/2024 10:54:21 Active

EPR de Flamanville 3 (Message 2/2)
Le volume d’électricité produite depuis le premier couplage jusqu’à l’arrêt programmé appelé « VC1 » sera de l’ordre de 14 TWh. 

Ce premier arrêt programmé pour rechargement du combustible devrait se situer majoritairement sur 2026. Son contenu, son organisation et la durée prévisionnelle en résultant font l’objet d’études en cours. 

EDF EDF-2024-00122 18/12/2024 10:51:36 Active

EPR de Flamanville 3 (Message 1/2)
Le premier couplage au réseau du réacteur EPR de Flamanville 3 est prévu le 20 décembre 2024. Après son couplage, le fonctionnement du réacteur sera marqué par différents paliers de puissance, jusqu’à l’été 2025, qui solderont la phase d’essais. 

A l’issue de cette période d’essais, il est prévu que le réacteur fonctionne à 100% de puissance jusqu'au premier arrêt programmé pour maintenance et rechargement du combustible, appelé Visite Complète 1 (VC1).

EDF EDF-2024-00286 17/12/2024 10:49:53 Active

Passage en DMO 32h pour Cordemais 4 à partir du 17/12 à 10h30 jusqu'à nouvel avis (28h pour le couplage et 4h pour atteindre la PMD)
-----------------------------
Switch to 32h DMO for Cordemais 4 from 17/12 at 10:30 am until further notice (28h for coupling and 4h to reach PMD)

European Regulation 1227/2011 on Wholesale Energy Market Integrity and Transparency (REMIT) requires producers to disclose to the public certain information concerning their assets. On this website you will find selected information related to planned and unplanned unavailability of EDF's production assets as well as other relevant information on the capacity and use of these assets.The unavailabilities planning of production units is EDF’s best estimate at publication time and it is based on the reasonable estimate of the time needed for the achievement of the planned maintenance on each unit.