      Please find a timeline regarding the shutdown of Nobelwind park.

      The tentative schedule is as follows:
      -    From 18/06 08:30 till 18/06 16:00
       Remaining capacity: 132MW
      -    From 19/06 08:30 till 19/06 09:30
        Remaining capacity: 132MW
      -    From 19/06 9:30 till 19/06 15:00
        Remaining capacity: 145.2MW
      -    From 19/06 15:00 till 19/06 16:00
         Remaining capacity: 132MW

      Regards,