LUM-2023-00207
-
Current version of the message - v4
-
Status : ActivePublication date : 17/06/2025 13:11:49Start date : 21/11/2023 16:21:44End date : 31/05/2026 00:00:00Company : LUMINUS
New unit Seraing CCGT (885 MW) under construction.
New unit (Seraing CCGT, 885 MW, unit EIC code: 22W20231025----2, 22W20231026----X) under construction.
Start testing phase with injection in the ELIA grid in the course of Q4 2025 subject to grid conditions. Unit available for commercial dispatching as of 31/05/2026.
-
-
Earlier version of the message - v3
-
Status : InactivePublication date : 25/02/2025 23:11:33Start date : 21/11/2023 16:21:44End date : 31/01/2026 00:00:00Company : LUMINUS
New unit Seraing CCGT (885 MW) under construction
New unit (Seraing CCGT, 885 MW) under construction. Start testing phase with injection in the ELIA grid in the course of Q2 2025 subject to grid conditions. Unit available for commercial dispatching as of 31/01/2026
-
-
Earlier version of the message - v2
-
Status : InactivePublication date : 17/09/2024 17:06:39Start date : 21/11/2023 16:21:44End date : 01/12/2025 00:00:00Company : LUMINUS
New unit Seraing CCGT (885 MW) under construction until 15/05/2025
New unit (Seraing CCGT, 885 MW) under construction until 15/05/2025. Start testing phase as of 15/05/2025 subject to grid conditions. Availability for security of supply of the new unit as of 1/11/2025 and availability for commercial dispatching on 01/12/2025
-
-
Earlier version of the message - v1
-
Status : InactivePublication date : 21/11/2023 16:23:15Start date : 21/11/2023 16:21:44End date : 01/11/2025 00:00:00Company : LUMINUS
New unit (Seraing CCGT) under construction until 30/01/2025. From 30/1/2025 to 31/10/2025 included: testing phase subject to grid conditions. Availability for the new unit: 01/11/25. The forecasts for the new CCGT at Seraing reflect Luminus' best vision at the time of publication and correspond to the reasonably foreseeable duration for the successful completion of construction activities.
-