EDF-2025-00188
-
Current version of the message - v2
-
Status : DismissedPublication date : 29/10/2025 18:07:26Start date : 29/10/2025 08:00:00End date : 29/10/2025 18:00:00Company : EDF
Passage en DMO 43 minutes pour la TAC Vaires 2 le 29 Octobre 2025 de 8h à 17h
-----------------------------
On October 29, 2025 from 8 a.m. to 5 p.m , coupling time for the Vaires 2 combustion turbine is increased to 43 minutes.
-
-
Earlier version of the message - v1
-
Status : InactivePublication date : 28/10/2025 19:33:33Start date : 29/10/2025 08:00:00End date : 29/10/2025 17:00:00Company : EDF
Passage en DMO 43 minutes pour la TAC Vaires 2 le 29 Octobre 2025 de 8h à 17h
-----------------------------
On October 29, 2025 from 8 a.m. to 5 p.m , coupling time for the Vaires 2 combustion turbine is increased to 43 minutes.
-