EDF-2024-00099

  • Current version of the message - v2
    • Status : Dismissed
      Publication date : 08/05/2024 18:50:53
      Start date : 27/03/2024 21:51:31
      Company : EDF

      End of message

  • Earlier version of the message - v1
    • Status : Inactive
      Publication date : 27/03/2024 21:51:41
      Start date : 27/03/2024 21:51:31
      Company : EDF

      Flamanville 3 EPR (Message 2/2)

       - The generated power volume from the first grid connection until the next planned outage is estimated at 14 TWh

       - The first planned outage, called “Visite Complète 1”, should mainly take place in 2026 and last several months. Its organization, content and subsequent duration are under construction