EDF-2023-00240
-
Current version of the message - v6
-
Status : DismissedPublication date : 09/09/2024 17:21:37Start date : 21/12/2023 15:51:12Company : EDF
Taking into account key learnings from controls and repairs undertaken in 2023 on reactors linked to stress corrosion cracking, EDF considers that, in 2023, one planned outage out of three for the following reactors may be extended by an average of 30 days.
The reactor(s) concerned : -
-
-
Earlier version of the message - v5
-
Status : InactivePublication date : 11/04/2024 12:13:26Start date : 21/12/2023 15:51:12Company : EDF
Taking into account key learnings from controls and repairs undertaken in 2023 on reactors linked to stress corrosion cracking, EDF considers that, in 2023, one planned outage out of three for the following reactors may be extended by an average of 30 days.
The reactor(s) concerned : BUG3.
-
-
Earlier version of the message - v4
-
Status : InactivePublication date : 28/03/2024 13:09:20Start date : 21/12/2023 15:51:12Company : EDF
Taking into account key learnings from controls and repairs undertaken in 2023 on reactors linked to stress corrosion cracking, EDF considers that, in 2023, one planned outage out of three for the following reactors may be extended by an average of 30 days.
The reactors concerned are: CHB1, BUG3.
-
-
Earlier version of the message - v3
-
Status : InactivePublication date : 29/02/2024 10:30:05Start date : 21/12/2023 15:51:12Company : EDF
Taking into account key learnings from controls and repairs undertaken in 2023 on reactors linked to stress corrosion cracking, EDF considers that, in 2023, one planned outage out of three for the following reactors may be extended by an average of 30 days.
The reactors concerned are: BLA2, CHB1, BUG3.
-
-
Earlier version of the message - v2
-
Status : InactivePublication date : 27/02/2024 10:42:29Start date : 21/12/2023 15:51:12Company : EDF
Taking into account key learnings from controls and repairs undertaken in 2023 on reactors linked to stress corrosion cracking, EDF considers that, in 2023, one planned outage out of three for the following reactors may be extended by an average of 30 days.
The reactors concerned are: BLA2, CHB1, BUG3, DAM3 .
-
-
Earlier version of the message - v1
-
Status : InactivePublication date : 21/12/2023 15:51:56Start date : 21/12/2023 15:51:12Company : EDF
Taking into account key learnings from controls and repairs undertaken in 2023 on reactors linked to stress corrosion cracking, EDF considers that, in 2023, one planned outage out of three for the following reactors may be extended by an average of 30 days.
The reactors concerned are: BLA2, GRA2, CHB1, BUG3, DAM3 .
-