EDF-2023-00222

  • Current version of the message - v5
    • Status : Dismissed
      Publication date : 04/12/2024 02:53:28
      Start date : 11/12/2023 19:28:46
      Company : EDF

      End of message

  • Earlier version of the message - v4
    • Status : Inactive
      Publication date : 06/06/2024 19:22:40
      Start date : 11/12/2023 19:28:46
      Company : EDF

      Publication on behalf of EDF-Renewables

      On June 6th 2024, 97 MW additional capacity of Parc Eolien Offshore des Hautes Falaises (Fécamp) has been commissioned.

      The dates for the main commissioning phases of the offshore wind farm are as follows

      100 MW: September 1st, 2023 (confirmed) 

      200 MW: December 11th 2023 (confirmed)

      300 MW: March 15th2024 (confirmed)

      400 MW: May 10th 2024 (confirmed)

      497 MW: June 6th 2024 (confirmed)

  • Earlier version of the message - v3
    • Status : Inactive
      Publication date : 29/04/2024 20:09:00
      Start date : 11/12/2023 19:28:46
      Company : EDF

      Publication on behalf of EDF-Renewables

      Offshore Windfarm under construction

      On March 15th 2024, 100 MW additional capacity of Parc Eolien Offshore des Hautes Falaises (Fécamp) has been commissioned.

       

      100 MW: September 1st, 2023 (confirmed)

      200 MW: December 11th 2023 (confirmed)

      300 MW: March 15th 2024 (confirmed)

      400 MW: April 29th 2024

      Estimated dates for next commissioning phases of the wind farm:

      497 MW: May 2024

      These dates will be updated on a regular basis during the commissioning process.

  • Earlier version of the message - v2
    • Status : Inactive
      Publication date : 15/03/2024 13:02:54
      Start date : 11/12/2023 19:28:46
      Company : EDF

      Publication on behalf of EDF-Renewables

      Offshore Windfarm under construction

      On March 15th 2024, 100 MW additional capacity of Parc Eolien Offshore des Hautes Falaises (Fécamp) has been commissioned.

       

      100 MW: September 1st, 2023 (confirmed)

      200 MW: December 11th 2023 (confirmed)

      300 MW: March 15th 2024 (confirmed)

       

      Estimated dates for next commissioning phases of the wind farm:

      400 MW: April 2024

      497 MW: May 2024

      These dates will be updated on a regular basis during the commissioning process.

  • Earlier version of the message - v1
    • Status : Inactive
      Publication date : 11/12/2023 19:29:05
      Start date : 11/12/2023 19:28:46
      Company : EDF

      Offshore Windfarm under construction

      On December 11th 2023, 100 MW additional capacity of Parc Eolien Offshore des Hautes Falaises (Fécamp) has been commissioned.

       

      100 MW: September 1st, 2023 (confirmed) 

      200 MW: December 11th 2023 (confirmed)

       

      Estimated dates for next commissioning phases of the wind farm:

      300 MW: January 2024

      400 MW: March 2024

      497 MW: April 2024

      These dates will be updated on a regular basis during the commissioning process.