05470_EDF_T_00300526

  • Current version of the outage - v3
    • Entity : Production
      Nom de la centrale : BANC DE GUERANDE
      Sector : Wind Offshore
      Location : France
      Market France
      Type : Planned
      Status : Actif
      Publication date : 29/05/2026 19:39:23
      Cause : Complementary informations
      Complementary informations :
      Le placement et la durée de l'indisponibilité peuvent être modifiés en fonction des conditions météorologiques afin de pouvoir accéder aux matériels en toute sécurité.
      --------
      The planning and the duration of this unavailability will be reassessed according to the weather's conditions, in order to ensure a safely access to the equipments.
      Between the : 01/06/2026 08:00:00
      and the : 01/06/2026 18:00:00
      360 MW
      MW AVAILABLE POWER
      480 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.

  • Earlier version of the outage - v2
    • Entity : Production
      Nom de la centrale : BANC DE GUERANDE
      Sector : Wind Offshore
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 29/05/2026 17:11:04
      Cause : Complementary informations
      Complementary informations :
      Le placement et la durée de l'indisponibilité peuvent être modifiés en fonction des conditions météorologiques afin de pouvoir accéder aux matériels en toute sécurité.
      --------
      The planning and the duration of this unavailability will be reassessed according to the weather's conditions, in order to ensure a safely access to the equipments.
      Between the : 01/06/2026 08:00:00
      and the : 01/06/2026 18:00:00
      240 MW
      MW AVAILABLE POWER
      480 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.

  • Earlier version of the outage - v1
    • Entity : Production
      Nom de la centrale : BANC DE GUERANDE
      Sector : Wind Offshore
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 22/05/2026 16:34:08
      Cause : Complementary informations
      Complementary informations :
      Le placement et la durée de l'indisponibilité peuvent être modifiés en fonction des conditions météorologiques afin de pouvoir accéder aux matériels en toute sécurité.
      --------
      The planning and the duration of this unavailability will be reassessed according to the weather's conditions, in order to ensure a safely access to the equipments.
      Between the : 01/06/2026 08:00:00
      and the : 02/06/2026 16:00:00
      354 MW
      MW AVAILABLE POWER
      480 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.