05470_EDF_T_00267027

  • Current version of the outage - v3
    • Entity : Generation
      Name : BLAYAIS 1
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Actif
      Publication date : 07/12/2025 16:10:17
      Cause : Complementary informations
      Complementary informations :
      Le placement et la durée de cet arrêt pour modulation seront réinterrogés et la tranche sera redémarrée si les conditions économiques le justifient
      La durée minimale d'arrêt est de 24h.
      --------
      The planning and duration of this unavailability for modulation supply will be reassessed and the plant will be restarted depending on economic conditions.
      The duration of the outage will be a least of 24 hours.
      Between the : 06/12/2025 01:00:00
      and the : 08/12/2025 05:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.

  • Earlier version of the outage - v2
    • Entity : Generation
      Name : BLAYAIS 1
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 06/12/2025 15:14:34
      Cause : Complementary informations
      Complementary informations :
      Le placement et la durée de cet arrêt pour modulation seront réinterrogés et la tranche sera redémarrée si les conditions économiques le justifient
      La durée minimale d'arrêt est de 24h.
      --------
      The planning and duration of this unavailability for modulation supply will be reassessed and the plant will be restarted depending on economic conditions.
      The duration of the outage will be a least of 24 hours.
      Between the : 06/12/2025 01:00:00
      and the : 08/12/2025 06:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.

  • Earlier version of the outage - v1
    • Entity : Generation
      Name : BLAYAIS 1
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 05/12/2025 15:23:38
      Cause : Complementary informations
      Complementary informations :
      Le placement et la durée de cet arrêt pour modulation seront réinterrogés et la tranche sera redémarrée si les conditions économiques le justifient
      La durée minimale d'arrêt est de 24h.
      --------
      The planning and duration of this unavailability for modulation supply will be reassessed and the plant will be restarted depending on economic conditions.
      The duration of the outage will be a least of 24 hours.
      Between the : 06/12/2025 01:00:00
      and the : 08/12/2025 00:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.