05470_EDF_T_00232357
-
Current version of the outage - v3
-
Entity : GenerationName : GRAVELINES 4Sector : NuclearLocation : FranceMarket FranceType : Chronique PMINStatus : ActifPublication date : 03/07/2025 22:40:14Cause : Complementary informationsComplementary informations :
PMIN
03/07/2025 00h00 : 360MW; 03h30 : 360MW; 03h35 : 362MW; 10h15 : 519MW; 10h25 : 523MW; 15h00 : 523MW; 15h05 : 525MW; 23h45 : 705MW; 23h50 : 707MW; 23h55 : 708MWBetween the : 03/07/2025 00:00:00and the : 04/07/2025 00:00:00The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v2
-
Entity : GenerationName : GRAVELINES 4Sector : NuclearLocation : FranceMarket FranceType : Chronique PMINStatus : InactivePublication date : 03/07/2025 12:08:34Cause : Complementary informationsComplementary informations :
PMIN
03/07/2025 00h00 : 360MW; 03h30 : 360MW; 03h35 : 362MW; 10h15 : 519MW; 10h25 : 523MW; 15h00 : 523MW; 15h05 : 525MW; 23h45 : 748MW; 23h55 : 752MWBetween the : 03/07/2025 00:00:00and the : 04/07/2025 00:00:00The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v1
-
Entity : GenerationName : GRAVELINES 4Sector : NuclearLocation : FranceMarket FranceType : Chronique PMINStatus : InactivePublication date : 03/07/2025 01:07:03Cause : Complementary informationsComplementary informations :
PMIN
03/07/2025 00h00 : 360MW; 03h30 : 360MW; 03h35 : 362MW; 20h15 : 774MW; 20h25 : 778MW; 23h55 : 778MWBetween the : 03/07/2025 00:00:00and the : 04/07/2025 00:00:00The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-