05470_EDF_T_00229615
-
Current version of the outage - v4
-
Entity : GenerationName : CIVAUX 1Sector : NuclearLocation : FranceMarket FranceType : Chronique PMINStatus : ActifPublication date : 20/06/2025 17:46:47Cause : Complementary informationsComplementary informations :
PMIN
20/06/2025 00h00 : 712MW; 17h25 : 712MW; 17h30 : 1396MW; 23h55 : 1396MWBetween the : 20/06/2025 00:00:00and the : 21/06/2025 00:00:00The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v3
-
Entity : GenerationName : CIVAUX 1Sector : NuclearLocation : FranceMarket FranceType : Chronique PMINStatus : InactivePublication date : 20/06/2025 17:32:47Cause : Complementary informationsComplementary informations :
PMIN
20/06/2025 00h00 : 712MW; 17h25 : 712MW; 17h30 : 1355MW; 23h55 : 1355MWBetween the : 20/06/2025 00:00:00and the : 21/06/2025 00:00:00The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v2
-
Entity : GenerationName : CIVAUX 1Sector : NuclearLocation : FranceMarket FranceType : Chronique PMINStatus : InactivePublication date : 20/06/2025 17:31:52Cause : Complementary informationsComplementary informations :
PMIN
20/06/2025 00h00 : 712MW; 17h25 : 712MW; 17h30 : 1400MW; 23h55 : 1400MWBetween the : 20/06/2025 00:00:00and the : 21/06/2025 00:00:00The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v1
-
Entity : GenerationName : CIVAUX 1Sector : NuclearLocation : FranceMarket FranceType : Chronique PMINStatus : InactivePublication date : 20/06/2025 17:31:37Cause : Complementary informationsComplementary informations :
PMIN
20/06/2025 00h00 : 712MW; 23h55 : 712MWBetween the : 20/06/2025 00:00:00and the : 21/06/2025 00:00:00The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-