05470_EDF_T_00192696
-
Current version of the outage - v2
-
Entity : GenerationName : BLAYAIS 4Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : ActifPublication date : 27/12/2024 09:46:03Cause : Foreseen MaintenanceComplementary informations :Between the : 27/12/2024 08:00:00and the : 27/12/2024 12:00:00600 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWER
The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v1
-
Entity : GenerationName : BLAYAIS 4Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 26/12/2024 18:52:29Cause : Foreseen MaintenanceComplementary informations :Between the : 27/12/2024 08:00:00and the : 27/12/2024 12:00:00644 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWER
The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-