05470_EDF_T_00147884
-
Current version of the outage - v5
-
Entity : GenerationName : NOGENT 1Sector : NuclearLocation : FranceMarket FranceType : ForcedStatus : ActifPublication date : 12/07/2024 15:11:52Cause : FailureComplementary informations :Between the : 08/07/2024 19:11:00and the : 12/07/2024 15:11:000 MWMW AVAILABLE POWER1310 MWMW MAXIMUM POWER
The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v4
-
Entity : GenerationName : NOGENT 1Sector : NuclearLocation : FranceMarket FranceType : ForcedStatus : InactivePublication date : 12/07/2024 08:35:22Cause : FailureComplementary informations :Between the : 08/07/2024 19:11:00and the : 12/07/2024 16:00:000 MWMW AVAILABLE POWER1310 MWMW MAXIMUM POWER
The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v3
-
Entity : GenerationName : NOGENT 1Sector : NuclearLocation : FranceMarket FranceType : ForcedStatus : InactivePublication date : 11/07/2024 18:03:50Cause : FailureComplementary informations :Between the : 08/07/2024 19:11:00and the : 12/07/2024 23:00:000 MWMW AVAILABLE POWER1310 MWMW MAXIMUM POWER
The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v2
-
Entity : GenerationName : NOGENT 1Sector : NuclearLocation : FranceMarket FranceType : ForcedStatus : InactivePublication date : 09/07/2024 10:01:35Cause : FailureComplementary informations :Between the : 08/07/2024 19:11:00and the : 14/07/2024 23:00:000 MWMW AVAILABLE POWER1310 MWMW MAXIMUM POWER
The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v1
-
Entity : GenerationName : NOGENT 1Sector : NuclearLocation : FranceMarket FranceType : ForcedStatus : InactivePublication date : 08/07/2024 19:12:15Cause : FailureComplementary informations :Between the : 08/07/2024 19:11:00and the : 09/07/2024 22:00:000 MWMW AVAILABLE POWER1310 MWMW MAXIMUM POWER
The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-