05470_EDF_T_00113339

  • Current version of the outage - v2
    • Entity : Generation
      Name : CRUAS 4
      Sector : Nuclear
      Location : France
      Market France
      Type : Chronic
      Status : Actif
      Publication date : 26/10/2023 16:31:38
      Cause : Complementary informations
      Complementary informations :
      PMIN
      27/10/2023 00h00 : 908MW; 23h55 : 908MW
      Between the : 27/10/2023 00:00:00
      and the : 28/10/2023 00:00:00

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.

  • Earlier version of the outage - v1
    • Entity : Generation
      Name : CRUAS 4
      Sector : Nuclear
      Location : France
      Market France
      Type : Chronic
      Status : Inactive
      Publication date : 26/10/2023 11:11:40
      Cause : Complementary informations
      Complementary informations :
      PMIN
      27/10/2023 00h00 : 908MW; 06h55 : 908MW; 07h00 : 772MW; 23h55 : 772MW
      28/10/2023 00h00 : 180MW; 23h55 : 180MW
      Between the : 27/10/2023 00:00:00
      and the : 28/10/2023 00:00:00

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.