05470_EDF_T_00090867
-
Current version of the outage - v20
-
Entity : GenerationName : FLAMANVILLE 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : ActifPublication date : 13/09/2026 22:16:12Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
Outage likely to be extended
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
Arrêt susceptible de se prolongerBetween the : 14/09/2026 09:00:00and the : 13/12/2026 22:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v19
-
Entity : GenerationName : FLAMANVILLE 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 13/09/2026 14:28:58Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
Outage likely to be extended
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
Arrêt susceptible de se prolongerBetween the : 14/09/2026 01:00:00and the : 13/12/2026 22:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v18
-
Entity : GenerationName : FLAMANVILLE 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 13/09/2026 06:46:18Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
Outage likely to be extended
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
Arrêt susceptible de se prolongerBetween the : 13/09/2026 17:00:00and the : 13/12/2026 22:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v17
-
Entity : GenerationName : FLAMANVILLE 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 12/09/2026 21:52:20Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
Outage likely to be extended
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
Arrêt susceptible de se prolongerBetween the : 13/09/2026 09:00:00and the : 13/12/2026 22:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v16
-
Entity : GenerationName : FLAMANVILLE 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 12/09/2026 14:33:06Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
Outage likely to be extended
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
Arrêt susceptible de se prolongerBetween the : 12/09/2026 23:30:00and the : 13/12/2026 22:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v15
-
Entity : GenerationName : FLAMANVILLE 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 12/09/2026 06:47:43Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
Outage likely to be extended
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
Arrêt susceptible de se prolongerBetween the : 12/09/2026 16:00:00and the : 13/12/2026 22:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v14
-
Entity : GenerationName : FLAMANVILLE 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 11/09/2026 22:26:09Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
Outage likely to be extended
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
Arrêt susceptible de se prolongerBetween the : 12/09/2026 09:00:00and the : 13/12/2026 22:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v13
-
Entity : GenerationName : FLAMANVILLE 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 11/09/2026 22:18:02Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
Outage likely to be extended
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
Arrêt susceptible de se prolongerBetween the : 12/09/2026 10:00:00and the : 13/12/2026 22:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v12
-
Entity : GenerationName : FLAMANVILLE 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 11/09/2026 15:08:44Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
Outage likely to be extended
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
Arrêt susceptible de se prolongerBetween the : 12/09/2026 01:00:00and the : 13/12/2026 22:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v11
-
Entity : GenerationName : FLAMANVILLE 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 04/09/2026 15:59:10Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
Outage likely to be extended
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
Arrêt susceptible de se prolongerBetween the : 11/09/2026 22:00:00and the : 13/12/2026 22:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v10
-
Entity : GenerationName : FLAMANVILLE 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 09/07/2026 18:41:12Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
Outage likely to be extended
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
Arrêt susceptible de se prolongerBetween the : 11/09/2026 22:00:00and the : 10/12/2026 22:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v9
-
Entity : GenerationName : FLAMANVILLE 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 19/06/2026 17:08:13Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 11/09/2026 22:00:00and the : 10/12/2026 22:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v8
-
Entity : GenerationName : FLAMANVILLE 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 28/05/2025 12:43:24Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 12/09/2026 00:00:00and the : 11/12/2026 00:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v7
-
Entity : GenerationName : FLAMANVILLE 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 28/03/2025 15:25:29Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 29/08/2026 00:00:00and the : 27/11/2026 00:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v6
-
Entity : GenerationName : FLAMANVILLE 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 31/01/2025 14:47:58Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 29/08/2026 00:00:00and the : 30/11/2026 00:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v5
-
Entity : GenerationName : FLAMANVILLE 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 19/07/2024 16:02:03Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 29/08/2026 00:00:00and the : 28/11/2026 00:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v4
-
Entity : GenerationName : FLAMANVILLE 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 29/03/2024 16:53:09Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 16/05/2026 00:00:00and the : 15/08/2026 00:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v3
-
Entity : GenerationName : FLAMANVILLE 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 20/12/2023 18:29:10Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 25/04/2026 02:00:00and the : 25/07/2026 02:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v2
-
Entity : GenerationName : FLAMANVILLE 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 21/07/2023 15:50:01Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 25/04/2026 02:00:00and the : 30/07/2026 02:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v1
-
Entity : GenerationName : FLAMANVILLE 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 25/04/2023 02:06:00Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 25/04/2026 02:00:00and the : 29/07/2026 02:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-