05470_EDF_T_00077028
-
Current version of the outage - v16
-
Entity : GenerationName : CHOOZ 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : ActifPublication date : 27/06/2025 16:34:00Cause : Complementary informationsComplementary informations :
Outage duration may be extended : https://doaat.edf.fr/message/edf-2023-00231
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Arrêt susceptible d'être prolongé : https://doaat.edf.fr/message/edf-2023-00230
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
Between the : 22/08/2025 22:00:00and the : 25/11/2025 22:00:000 MWMW AVAILABLE POWER1500 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v15
-
Entity : GenerationName : CHOOZ 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 29/03/2025 08:16:14Cause : Complementary informationsComplementary informations :
Outage duration may be extended : https://doaat.edf.fr/message/edf-2023-00231
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Arrêt susceptible d'être prolongé : https://doaat.edf.fr/message/edf-2023-00230
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
Between the : 23/08/2025 00:00:00and the : 26/11/2025 00:00:000 MWMW AVAILABLE POWER1500 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v14
-
Entity : GenerationName : CHOOZ 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 19/07/2024 16:03:30Cause : Complementary informationsComplementary informations :
Outage duration may be extended : https://doaat.edf.fr/message/edf-2023-00231
The operation of this unit is already constrained by its fuel stock: lowering production too frequently would necessitate the postponement of this shutdown.
Arrêt susceptible d'être prolongé : https://doaat.edf.fr/message/edf-2023-00230
Le fonctionnement de cette tranche est dès à présent contraint par son stock de combustible : des baisses de production trop fréquentes nécessiteraient un report de cet arrêt.
Between the : 23/08/2025 00:00:00and the : 26/11/2025 00:00:000 MWMW AVAILABLE POWER1500 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v13
-
Entity : GenerationName : CHOOZ 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 12/07/2024 16:23:11Cause : Complementary informationsComplementary informations :
Outage duration may be extended : https://doaat.edf.fr/message/edf-2023-00231
The operation of this unit is already constrained by its fuel stock: lowering production too frequently would necessitate the postponement of this shutdown.
Arrêt susceptible d'être prolongé : https://doaat.edf.fr/message/edf-2023-00230
Le fonctionnement de cette tranche est dès à présent contraint par son stock de combustible : des baisses de production trop fréquentes nécessiteraient un report de cet arrêt.
Between the : 23/08/2025 00:00:00and the : 28/11/2025 00:00:000 MWMW AVAILABLE POWER1500 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v12
-
Entity : GenerationName : CHOOZ 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 29/03/2024 16:54:38Cause : Complementary informationsComplementary informations :
Outage duration may be extended : https://doaat.edf.fr/message/edf-2023-00231
The operation of this unit is already constrained by its fuel stock: lowering production too frequently would necessitate the postponement of this shutdown.
Arrêt susceptible d'être prolongé : https://doaat.edf.fr/message/edf-2023-00230
Le fonctionnement de cette tranche est dès à présent contraint par son stock de combustible : des baisses de production trop fréquentes nécessiteraient un report de cet arrêt.
Between the : 16/08/2025 02:00:00and the : 21/11/2025 00:00:000 MWMW AVAILABLE POWER1500 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v11
-
Entity : GenerationName : CHOOZ 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 21/02/2024 10:58:12Cause : Complementary informationsComplementary informations :
Outage duration may be extended : https://doaat.edf.fr/message/edf-2023-00231
The operation of this unit is already constrained by its fuel stock: lowering production too frequently would necessitate the postponement of this shutdown.
Arrêt susceptible d'être prolongé : https://doaat.edf.fr/message/edf-2023-00230
Le fonctionnement de cette tranche est dès à présent contraint par son stock de combustible : des baisses de production trop fréquentes nécessiteraient un report de cet arrêt.
Between the : 16/08/2025 02:00:00and the : 03/12/2025 02:00:000 MWMW AVAILABLE POWER1500 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v10
-
Entity : GenerationName : CHOOZ 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 21/12/2023 14:59:49Cause : Complementary informationsComplementary informations :
Outage duration may be extended : https://doaat.edf.fr/message/edf-2023-00231
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Arrêt susceptible d'être prolongé : https://doaat.edf.fr/message/edf-2023-00230
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 16/08/2025 02:00:00and the : 03/12/2025 02:00:000 MWMW AVAILABLE POWER1500 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v9
-
Entity : GenerationName : CHOOZ 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 21/12/2023 14:49:01Cause : Complementary informationsComplementary informations :
Outage duration may be extended : https://doaat.edf.fr/message/edf-2023-00231
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Arrêt susceptible d'être prolongé : https://doaa.edf.fr/message/edf-2023-00230
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 16/08/2025 02:00:00and the : 03/12/2025 02:00:000 MWMW AVAILABLE POWER1500 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v8
-
Entity : GenerationName : CHOOZ 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 21/07/2023 15:51:42Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 16/08/2025 02:00:00and the : 03/12/2025 02:00:000 MWMW AVAILABLE POWER1500 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v7
-
Entity : GenerationName : CHOOZ 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 15/06/2023 18:29:55Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 16/08/2025 02:00:00and the : 05/12/2025 02:00:000 MWMW AVAILABLE POWER1500 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v6
-
Entity : GenerationName : CHOOZ 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 31/03/2023 17:38:21Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 20/09/2025 02:00:00and the : 09/01/2026 02:00:000 MWMW AVAILABLE POWER1500 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v5
-
Entity : GenerationName : CHOOZ 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 04/01/2023 14:57:30Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 20/09/2025 02:00:00and the : 11/01/2026 02:00:000 MWMW AVAILABLE POWER1500 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v4
-
Entity : GenerationName : CHOOZ 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 16/12/2022 22:42:58Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 20/09/2025 02:00:00and the : 28/12/2025 02:00:000 MWMW AVAILABLE POWER1500 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v3
-
Entity : GenerationName : CHOOZ 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 07/10/2022 14:21:32Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 02/08/2025 02:00:00and the : 09/11/2025 02:00:000 MWMW AVAILABLE POWER1500 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v2
-
Entity : GenerationName : CHOOZ 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 05/08/2022 16:16:41Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 14/06/2025 02:00:00and the : 21/09/2025 02:00:000 MWMW AVAILABLE POWER1500 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v1
-
Entity : GenerationName : CHOOZ 1Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 14/06/2022 02:16:10Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 14/06/2025 02:00:00and the : 19/09/2025 02:00:000 MWMW AVAILABLE POWER1500 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-