05470_EDF_H_00117657
-
Current version of the outage - v1
-
Entity : ProductionNom de la centrale : MONTEZICSector : Hydro pumped storageLocation : FranceMarket FranceType : PlannedStatus : ActifPublication date : 08/07/2025 16:35:28Cause : Foreseen MaintenanceComplementary informations :Between the : 20/07/2026 14:00:00and the : 20/07/2026 18:00:000 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWER
The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-