05470_EDF_H_00114910

  • Current version of the outage - v2
    • Entity : Generation
      Name : COMBE D'AVRIEUX 1
      Sector : Hydro Water Reservoir
      Location : France
      Market France
      Type : Forced
      Status : Actif
      Publication date : 17/04/2025 12:24:41
      Cause : Failure
      Complementary informations :
      La durée indiquée dans la première version est une durée par défaut qui sera affinée après analyse technique - The duration indicated in the first version is pre-defined and will be reassessed after technical analysis.
      Between the : 17/04/2025 05:19:00
      and the : 17/04/2025 12:22:00
      0 MW
      MW AVAILABLE POWER
      123 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.

  • Earlier version of the outage - v1
    • Entity : Generation
      Name : COMBE D'AVRIEUX 1
      Sector : Hydro Water Reservoir
      Location : France
      Market France
      Type : Forced
      Status : Inactive
      Publication date : 17/04/2025 05:23:13
      Cause : Failure
      Complementary informations :
      La durée indiquée dans la première version est une durée par défaut qui sera affinée après analyse technique - The duration indicated in the first version is pre-defined and will be reassessed after technical analysis.
      Between the : 17/04/2025 05:19:00
      and the : 17/04/2025 17:00:00
      0 MW
      MW AVAILABLE POWER
      123 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.