05470_EDF_T_00179526
-
Current version of the outage - v9
-
Entity : GenerationName : ST ALBAN 1Sector : NuclearLocation : FranceMarket FranceType : ForcedStatus : ActifPublication date : 18/10/2024 09:50:41Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
-----------------------------------------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48hBetween the : 15/10/2024 20:59:00and the : 18/10/2024 11:30:000 MWMW AVAILABLE POWER1335 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v8
-
Entity : GenerationName : ST ALBAN 1Sector : NuclearLocation : FranceMarket FranceType : ForcedStatus : InactivePublication date : 18/10/2024 07:14:35Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
-----------------------------------------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48hBetween the : 15/10/2024 20:59:00and the : 18/10/2024 10:00:000 MWMW AVAILABLE POWER1335 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v7
-
Entity : GenerationName : ST ALBAN 1Sector : NuclearLocation : FranceMarket FranceType : ForcedStatus : InactivePublication date : 18/10/2024 04:17:22Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
-----------------------------------------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48hBetween the : 15/10/2024 20:59:00and the : 18/10/2024 08:00:000 MWMW AVAILABLE POWER1335 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v6
-
Entity : GenerationName : ST ALBAN 1Sector : NuclearLocation : FranceMarket FranceType : ForcedStatus : InactivePublication date : 17/10/2024 18:30:37Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
-----------------------------------------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48hBetween the : 15/10/2024 20:59:00and the : 18/10/2024 06:00:000 MWMW AVAILABLE POWER1335 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v5
-
Entity : GenerationName : ST ALBAN 1Sector : NuclearLocation : FranceMarket FranceType : ForcedStatus : InactivePublication date : 17/10/2024 14:22:38Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
-----------------------------------------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48hBetween the : 15/10/2024 20:59:00and the : 17/10/2024 21:00:000 MWMW AVAILABLE POWER1335 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v4
-
Entity : GenerationName : ST ALBAN 1Sector : NuclearLocation : FranceMarket FranceType : ForcedStatus : InactivePublication date : 16/10/2024 18:59:47Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
-----------------------------------------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48hBetween the : 15/10/2024 20:59:00and the : 18/10/2024 23:00:000 MWMW AVAILABLE POWER1335 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v3
-
Entity : GenerationName : ST ALBAN 1Sector : NuclearLocation : FranceMarket FranceType : ForcedStatus : InactivePublication date : 15/10/2024 23:20:14Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
-----------------------------------------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48hBetween the : 15/10/2024 20:59:00and the : 17/10/2024 00:00:000 MWMW AVAILABLE POWER1335 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v2
-
Entity : GenerationName : ST ALBAN 1Sector : NuclearLocation : FranceMarket FranceType : ForcedStatus : InactivePublication date : 15/10/2024 21:23:27Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
-----------------------------------------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48hBetween the : 15/10/2024 20:59:00and the : 16/10/2024 21:00:000 MWMW AVAILABLE POWER1335 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-
-
Earlier version of the outage - v1
-
Entity : GenerationName : ST ALBAN 1Sector : NuclearLocation : FranceMarket FranceType : ForcedStatus : InactivePublication date : 15/10/2024 21:00:33Cause : Complementary informationsComplementary informations :
La durée indiquée de l'indisponibilité correspond à une durée forfaitaire de 24h, évaluée sur la base du retour d'expérience sur le parc nucléaire.
Une nouvelle version sera publiée en fonction des diagnostics et des analyses qui seront réalisés.
--------
The duration of the unavailability is a pre-defined 24 hours period, assessed on the basis of the nuclear fleet feedback
A new version will be published according to diagnostic and technical instruction.Between the : 15/10/2024 20:59:00and the : 16/10/2024 21:00:000 MWMW AVAILABLE POWER1335 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
-