05470_EDF_T_00179526

  • Current version of the outage - v9
    • Entity : Generation
      Name : ST ALBAN 1
      Sector : Nuclear
      Location : France
      Market France
      Type : Forced
      Status : Actif
      Publication date : 18/10/2024 09:50:41
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
      -----------------------------------------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h
      Between the : 15/10/2024 20:59:00
      and the : 18/10/2024 11:30:00
      0 MW
      MW AVAILABLE POWER
      1335 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.

  • Earlier version of the outage - v8
    • Entity : Generation
      Name : ST ALBAN 1
      Sector : Nuclear
      Location : France
      Market France
      Type : Forced
      Status : Inactive
      Publication date : 18/10/2024 07:14:35
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
      -----------------------------------------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h
      Between the : 15/10/2024 20:59:00
      and the : 18/10/2024 10:00:00
      0 MW
      MW AVAILABLE POWER
      1335 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.

  • Earlier version of the outage - v7
    • Entity : Generation
      Name : ST ALBAN 1
      Sector : Nuclear
      Location : France
      Market France
      Type : Forced
      Status : Inactive
      Publication date : 18/10/2024 04:17:22
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
      -----------------------------------------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h
      Between the : 15/10/2024 20:59:00
      and the : 18/10/2024 08:00:00
      0 MW
      MW AVAILABLE POWER
      1335 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.

  • Earlier version of the outage - v6
    • Entity : Generation
      Name : ST ALBAN 1
      Sector : Nuclear
      Location : France
      Market France
      Type : Forced
      Status : Inactive
      Publication date : 17/10/2024 18:30:37
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
      -----------------------------------------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h
      Between the : 15/10/2024 20:59:00
      and the : 18/10/2024 06:00:00
      0 MW
      MW AVAILABLE POWER
      1335 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.

  • Earlier version of the outage - v5
    • Entity : Generation
      Name : ST ALBAN 1
      Sector : Nuclear
      Location : France
      Market France
      Type : Forced
      Status : Inactive
      Publication date : 17/10/2024 14:22:38
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
      -----------------------------------------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h
      Between the : 15/10/2024 20:59:00
      and the : 17/10/2024 21:00:00
      0 MW
      MW AVAILABLE POWER
      1335 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.

  • Earlier version of the outage - v4
    • Entity : Generation
      Name : ST ALBAN 1
      Sector : Nuclear
      Location : France
      Market France
      Type : Forced
      Status : Inactive
      Publication date : 16/10/2024 18:59:47
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
      -----------------------------------------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h
      Between the : 15/10/2024 20:59:00
      and the : 18/10/2024 23:00:00
      0 MW
      MW AVAILABLE POWER
      1335 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.

  • Earlier version of the outage - v3
    • Entity : Generation
      Name : ST ALBAN 1
      Sector : Nuclear
      Location : France
      Market France
      Type : Forced
      Status : Inactive
      Publication date : 15/10/2024 23:20:14
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
      -----------------------------------------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h
      Between the : 15/10/2024 20:59:00
      and the : 17/10/2024 00:00:00
      0 MW
      MW AVAILABLE POWER
      1335 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.

  • Earlier version of the outage - v2
    • Entity : Generation
      Name : ST ALBAN 1
      Sector : Nuclear
      Location : France
      Market France
      Type : Forced
      Status : Inactive
      Publication date : 15/10/2024 21:23:27
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
      -----------------------------------------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h
      Between the : 15/10/2024 20:59:00
      and the : 16/10/2024 21:00:00
      0 MW
      MW AVAILABLE POWER
      1335 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.

  • Earlier version of the outage - v1
    • Entity : Generation
      Name : ST ALBAN 1
      Sector : Nuclear
      Location : France
      Market France
      Type : Forced
      Status : Inactive
      Publication date : 15/10/2024 21:00:33
      Cause : Complementary informations
      Complementary informations :
      La durée indiquée de l'indisponibilité correspond à une durée forfaitaire de 24h, évaluée sur la base du retour d'expérience sur le parc nucléaire.
      Une nouvelle version sera publiée en fonction des diagnostics et des analyses qui seront réalisés.
      --------
      The duration of the unavailability is a pre-defined 24 hours period, assessed on the basis of the nuclear fleet feedback
      A new version will be published according to diagnostic and technical instruction.
      Between the : 15/10/2024 20:59:00
      and the : 16/10/2024 21:00:00
      0 MW
      MW AVAILABLE POWER
      1335 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.